Gamka Dam,
Beaufort West - February 2002
CLIENT:Dept. of Water Affairs and Forestry
CONSULTING ENGINEERS:ROTEK
SCOPE OF WORK:
- Removal and replacement of sluice gate rails.
- 30 meters of vertical rails of approximately 150kg each. Water depth 0
to 18 meters.
- Visibility 0.03meters with use of artificial lighting.
- Bolts being corroded and with limited visibility, existing rails had to
be removed using Brocco Cutting and hoisted to top of tower for disposal.
- New Holes could not be drilled with rails insitu, hence accurate marking
and drilling was required with the allowable hole tolerance of 3mm.
-
Custom drilling equipment was required to drill a primary
M20 hole through 40mm of steel, followed by an M18 core hole, 120mm into
reinforced concrete.
- Rails were fastened using M16, A4 Hilti Hit500RE chemical anchors
- Rails needed to be carefully manouvered to avoid damage to the 1.5mm of
anti corrosive paint spec.